One of the key factors that determines the value of real estate is the “road”. How the land you intend to buy adjoins which kind of road affects both its usability and its value. Information about roads is therefore given particular weight in real estate transactions.
“Roads” come in many different kinds. A road may look perfectly ordinary, yet on closer inspection turn out to have problems — and buying such a property without knowing could lead to a serious mistake.

※ Even on a flag-shaped lot, a building can in principle be constructed if the lot adjoins a road at least 4 m wide for at least 2 m.However, the access passage leading to the road (the “pole” part of the lot) must be at least 2 m wide even at its narrowest point (local ordinances may require a greater width depending on the length of the passage).

Example of a flag-shaped lot: the building stands at the far end of the passage

“Existing Non-conforming” and “No Rebuilding Permitted”
The Building Standards Act imposes a road-frontage obligation, yet in reality there are a great many buildings that do not satisfy the requirement of “adjoining a road at least 4 m wide for at least 2 m”.
You will sometimes see several houses lined up along a narrow road less than 3 m wide. Are these buildings “illegal buildings” that violate the Building Standards Act?

The building on the left is not illegal, but it does not meet the requirements of the current Building Standards Act. It may be in a so-called “existing non-conforming” state (“Article 42-2 roads”, described below, are an exception).

“Existing non-conforming” refers to a building constructed under older laws, or to that state. It was lawful under the standards of the time, but no longer conforms to current law because of later amendments to the Building Standards Act and the like.
It differs from an “illegal building” in that it was lawful when it was built.

The concept of existing non-conformity
In other words, the building in the picture above stands along a road less than 3 m wide, but it may well have been lawful under the standards in force when it was built.

Incidentally, existing non-conformity is not limited to breaches of the road-frontage obligation. For example, if a factory was built before a land use zone was set by the city plan and the site was later designated an “exclusively residential zone”, the factory becomes “existing non-conforming”.
In principle such a property may continue to be used as it is (although it may have to be brought into line with current law when it is extended or undergoes major repairs). However, if the existing building is demolished and rebuilt, the new building must comply with current law. On a site that does not meet the road-frontage obligation, as a rule no new building can be constructed.
This is the state known as “no rebuilding permitted”, and buildings standing on sites such as the following all fall into this category.

Examples of sites where rebuilding is not permitted
Properties on which rebuilding is not permitted are often offered at prices below the local market. The reason is that they are hard to sell later precisely because they cannot be rebuilt.
Because the building cannot be rebuilt, buyers have limited uses for it and find it difficult to obtain a bank loan. Its value as real estate is therefore naturally lower.
However, if “certification” or “permission” under Article 43(2) of the Building Standards Act is obtained (permission requires the consent of the Building Review Board), building may be possible even on a site that does not meet the road-frontage obligation.


How to Measure the Width of a Road
As a rule, the width of a road is measured between the boundary lines of the road and the site. Where a gutter (an L-shaped gutter in the photo) lies within the road area, it is generally included in the road width, but practice differs between local authorities, so it is important to check with the city office. Where there is a pavement beside the road, the pavement and the kerb on its inner side are also included in the road.


If the gutter is within the road area, it is generally included when measuring the road width / on roads with a pavement, the pavement is also part of the road

What matters is whether it is a “road under the Building Standards Act”. Not every way counts as a “road” here — it must be a “road recognised by the Building Standards Act”.

Some ways look like roads but are not recognised as roads under the Building Standards Act. Note that a building adjoining such a way does not satisfy the road-frontage obligation unless the way is a road under the Act.

Example of a way that is not a road under the Building Standards Act.
※ It is asphalt-paved, and at a glance cannot be distinguished from other roads

To find out whether a road is a road under the Building Standards Act, ask at the city office counter in charge of building confirmation and building guidance; some local authorities also publish road information online so that you can check it yourself.
Roads in the rural areas of Ishigaki City are often “farm roads” managed by the city, which are not “roads under the Building Standards Act”. However, a building may be permitted if you obtain “consent to use the farm road for construction” from Ishigaki City as its manager and then receive certification or permission under Article 43(2) of the Act. Please confirm the specific procedures and requirements with the relevant section of Ishigaki City.
For other municipalities, a web search for the keywords “(name of the municipality) + designated road map” should find the information.


Types of Road
Roads are defined in Article 42 of the Building Standards Act. Basically, only the roads defined there are the “roads under the Building Standards Act” mentioned above. These roads come in several types, each classified and defined under a different provision.

Main types of road under the Building Standards Act
It is easier to picture what each type of road actually looks like from photos of the roads we see every day. Examples of each are shown below.
Of these, you are likely to hear terms such as “Article 42-2 roads” and “position-designated roads” in real estate investment practice.
■ Article 42(1)(i) road (Item 1 road)

Example of an Article 42(1)(i) road
A road at least 4 m wide that is maintained and managed by the prefecture, municipality or similar. National roads, prefectural roads and municipal roads fall into this category.
Item 1 roads are often described as “roads under the Road Act”. The Road Act is the law governing national expressways, general national roads, prefectural roads and municipal roads, and Item 1 roads are basically all “public roads”.

■ Article 42(1)(ii) road (Item 2 road)

Example of an Article 42(1)(ii) road

A road at least 4 m wide built under the City Planning Act, the Land Readjustment Act, the Urban Renewal Act and the like — for example, roads built as part of residential development in urban areas. After development they may become Item 1 roads under the management of the prefecture or municipality.

■ Article 42(1)(iii) road (existing road)

Example of an Article 42(1)(iii) road

A way that was already at least 4 m wide when the road provisions of the Building Standards Act came to apply (for example, when the area was designated a city planning area; the date varies by area). It refers to ways that are not Item 1 roads (roads under the Road Act), and may be private roads.

■ Article 42(1)(iv) road (planned road)

The fenced area on the left of the photo is an Article 42(1)(iv) road

A road for which there is a plan for new construction or alteration under the Road Act, the City Planning Act or the like, and which the designated administrative agency has designated as due to be built within two years. In practice, a fenced-off strip alongside an existing road, as in the photo, is an example. Even though it cannot yet be used, it is recognised as a road under the Building Standards Act.

■ Article 42(1)(v) road (position-designated road)

Example of an Article 42(1)(v) road (position-designated road).

Commonly called a “position-designated road”. For example, when a large plot is subdivided, the lots at the back may be unable to meet the road-frontage obligation and so cannot be built on.
In such cases, a road is created after the designated administrative agency designates “this position on this site as a road”. Because part of the site becomes a road, position-designated roads are basically all “private roads”.


Mini-developments and position-designated roads
A typical example of a position-designated road is the “mini-development” — dividing a plot of land below the size that requires development permission and building several houses on it.

The area requiring development permission varies by zone: in principle 1,000 m² or more in urbanisation promotion areas (500 m² or more in parts of the three major metropolitan areas), 3,000 m² or more in city planning areas without zoning division (non-delineated areas) such as Ishigaki City, and 1 ha or more outside city planning areas (in urbanisation control areas, permission is in principle required regardless of size). Mini-developments, which divide land below the size requiring permission, have therefore been widespread in urban areas.
In a mini-development, some of the divided lots cannot meet the frontage requirement, so part of the site is made a position-designated road to satisfy the road-frontage obligation.

A plot is divided into several lots, and a position-designated road is laid out in the centre so that a building can be put on each.
※ Position-designated roads often come into being through mini-developments like this

An actual mini-development, commonly seen in urban residential areas


■ Article 42(2) road (Item 2 road, deemed road), commonly called an “Article 42(2) road”

The road in the photo above was originally less than 4 m wide. As it was later designated an Article 42(2) road, the owner of the building in the foreground presumably set the building back before rebuilding.
The part of the site that is set back is given over to the road (private road burden), so no building can be placed there. The site effectively becomes smaller, so care is needed when buying a site that will require a setback in future.

Article 43 of the Building Standards Act states that “the site of a building must adjoin a road (…) for at least 2 m” (quoted from the Building Standards Act). To build a house that complies with the Act, the site must adjoin a “road” as defined by the Act for at least 2 m, so whether the way adjoining the site is recognised as a “road” under the Act is crucial.

Article 42(1) of the Act defines a road, in principle, as one at least 4 m wide (6 m in areas designated by the administrative agency), but as there are many roads under 4 m wide in built-up areas,Article 42(2) of the Building Standards Act deems ways designated by the administrative agency to be “roads” even if they are less than 4 m wide.
On an Article 42(2) road, the line 2 m horizontally from the centre line of the road is, in principle, deemed to be the road boundary (where one side of the way is a cliff or river, the line 4 m from the boundary on the opposite side). For this reason, even on land you own, you may not build a building or wall on the road side of that line.
An Article 42(2) road is a way less than 4 m wide, already lined with buildings when the road provisions of the Building Standards Act came to apply, that has been designated by the administrative agency; such roads are deemed roads under the Act even though they are less than 4 m wide.
Normally rebuilding would not be possible because the road is under 4 m, but on an Article 42(2) road rebuilding becomes possible by “setting the site back 2 m from the centre of the road”.


Article 42(2) roads and the concept of setback
Even if the road is only 3 m wide, a 4 m road will be secured in the future if the buildings on both sides are set back when rebuilt.
In other words, Article 42(2) roads serve as a relief measure for existing roads.
Under the Urban Building Act (applied mainly to large cities), the predecessor of the Building Standards Act, roads were originally required to be at least 9 shaku (about 2.7 m) wide, so many buildings still stand along ways less than 4 m wide. Article 42(2) roads exist so that rebuilding can be permitted on such roads provided a width of 4 m can be secured in the future.

Public Roads and Private Roads
Although there is no clear legal definition, roads are commonly classified as “public roads” and “private roads”. A “public road” is one provided and maintained by the government for traffic, such as a national, prefectural or municipal road; a “private road” is one built, maintained and managed by an individual or organisation. The distinction is “whether the managing body is public or private”.

※ Whether a road is “a road under the Building Standards Act”, as described above, has no direct connection with whether it is “public or private”. Even a private road allows building if it is an Item 3 road, a position-designated road or an Article 42(2) road, as described earlier.